BPCS/LX Tip of the Week: Facility Period Close

The Facility Period Close process, as introduced in Infor LX 8.3.4, was designed to function interactively. 

The expectation was that clients with a continuous or 24-hour worldwide operation in multiple facilities would submit the Period End Close jobs for each facility as daily operations ceased or shifts ended for each facility. This process was designed to function interactively so that validations of users performing transactions that conflicted with period end processing, and resulting messages, were immediately sent to the period end user. 

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process. For example, a user has a 24-hour operation in facilities around the world, but a centralized IT operation. With this enhancement the user can submit the individual facilities to be closed to a batch process that can be managed by a scheduler, automatically releasing each facility to be closed at a predetermined time.

Previous Article Flexfab Expands Their Use of Crossroads RMC Data Collection for All LN Installations Globally
Next Article Pushing Forward In the Face of Adversity. Soundview recently suffered a major loss when fire struck on January 30, 2019.
Print
57149 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

▪ Define a type C inventory transaction.

▪ Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

▪ Enter the information for the actual cost transaction on the appropriate lines.