Infor LX & BPCS Tip: Infor LX & BPCS Cycle Counting Selection Process

The cycle counting sub-system in Inventory Management determines which items are selected for cycle counting based on the following criteria:

  1. Cycle Counts/Year: The system calculates the cycle count frequency for each item using the "Cycle Counts/Year" field in the Item Master file (optional).

  2. Last Cycle Count Date: If you use locations, this date is found in the Location Inventory file (ILI), and if you don't, it's in the Warehouse Inventory file (IWI).

The system adds the calculated cycle count frequency to the last cycle count date. If the result is less than or equal to today's date, the item is selected for cycle counting. If it's greater, the item is not due for cycle counting yet.

Additionally, an item is automatically selected for cycle counting if the Cycle Flag field in the ILI/IWI record contains 'Y.' This flag indicates that the item's on-hand balance has gone negative since the last cycle count, even if it's not negative at the time of selection. The programs INV500D, INV510, and BIL540 can set this flag.

You can further narrow down the selection of items by specifying item number or warehouse limits.

Previous Article "Apologies, boss, but at the moment, we are unable to contribute to advancing the business."
Next Article Infor LX & BPCS Tip: How to handle “ZERO COST” items
Print
23180 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

▪ Define a type C inventory transaction.

▪ Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

▪ Enter the information for the actual cost transaction on the appropriate lines.