OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
27821 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

▪ Define a type C inventory transaction.

▪ Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

▪ Enter the information for the actual cost transaction on the appropriate lines.