Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
16394 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.
First141142143144146148149150Last

Theme picker

Tips: LN | Baan

Companies are developing procedures for entering data into an ERP system and for archiving manuals, drawings, specs, and other hard-copy documents. However, in many cases there is no defined procedures to store historical electronic data. Archiving electronic data should be an integral part of your business processes. 

Generally, archiving is the process of moving historical data from the operational environment to a special archive environment. At home, you might move old bank statements from a closet in your study to a box in the attic. At the office, you might store old hard copies of purchase orders in a room far from your own desk. Just because you no longer need the information in your daily work, does not mean you can dispose of the information. In terms of electronic data in your ERP system, archiving means moving historic data from the operational company to a special archive company; in that way, the historic data will be out of your way and safely stored. To free up disk space on your machine after you have archived the data, you can also move the historic data to an external medium.

Archiving strategy:

You can block a warehouse for inbound procedures, outbound procedures, or both. For example, you can block inbound and outbound procedures for a warehouse if the warehouse must be closed temporarily for inspection.

You can impose these types of blockings:

  • Full block: Full block on warehousing procedures.

  • Interactive block: Override blocking allowed except blocks on confirm shipment or confirm receipt.

If you impose a full block on inbound procedures...

1345678910Last

Theme picker

Categories