Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
31560 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Define Inventory transactions for issuing components to the shop and receiving finished items. See the Inventory help text for examples of transactions.

  • Transaction type I - Single Issue to Shop Order. Use this transaction type to issue one component at a time. Use this for high-value items that are marked as Must Single Issue on the Item Master file.
  • Transaction type M - Multiple Issue to Shop Order. Use this transaction type to issue all the components as listed in the Shop Order, in one transaction. Note that this transaction type does not issue Must Single Issue items.
  • Transaction type S - Receipt from shop. Use this transaction type to receive the finished item into stock and update the shop order accordingly. 

The Shop Order Lot/Location Allocation program is an alternative to using the above Inventory transactions. Use this when the item is finished, and you want to review exactly what was used to make it. You can review the components as allocated, make any changes, and finally accept the finished order.

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

FirstLast

Tips: LN | Baan

Users can personalize sessions and apply special formatting to the data displayed in sessions. The personalizations and formatting settings that are specified by the users are stored on the LN server. Administrators can maintain these settings.

  • Session personalizations

    Users can personalize sessions in various ways. users can, for example, hide fields, change labels, customize the toolbar, and move fields to another tab. Administrators can maintain the personalizations defined by the users. For example, an administrator can export personalizations to an XML file, import personalizations from an XML file, and copy personalizations to another user, to a DEM role, or to a company number.

  • Report personalizations

    You can use the Report Designer (ttstppersrep) to personalize the layouts and style of reports, without modifying the standard reports or using an external reporting solution. The changes are stored as personalizations.

    You can also generate new reports that are based on a selection of fields from the application data model. These reports are generated in the extensibility package. You can personalize these reports in the Report Designer (ttstppersrep), or modify them in Infor LN Studio.

    For details, see the Infor LN Report Designer Development Guide
     
  • Conditional formatting

    users can define conditions to apply special formatting to the data displayed in LN sessions. The users can define multiple conditions per session and different types of formatting, such as a specific color for particular fields or rows, and a warning symbol for particular rows. Administrators can maintain the formatting settings specified by the users and can define system-wide formatting settings.

  • If Finances is implemented, we recommend that you do not delete order data in a fiscal year that has not yet been fully closed. This is because the GRINYA process uses information that would be deleted by this action. For best results, check whether the logistical balance for non-invoiced receipts matches the balance of the GRINYA accounts for the periods up to which you want to delete purchase order data.
  • When a purchase order is canceled, you can only delete the purchase order and the related tables. If only a purchase order line is canceled, the line can be deleted and archived.

You cannot delete a purchase order (line) if:

  • The linked warehouse order is closed but cannot be removed.
  • The purchase order is linked to a PCS project that is not yet archived. When the PCS project is archived, the purchase data is also archived and you can delete the purchase order.
  • A consignment replenishment order is not yet consumed completely.
  • The invoice is yet to be completely matched and approved.
  • The invoice amount is not yet inserted as turnover history.
  • The sales order or service order that is linked to the purchase order line, and for which an internal invoice must be sent from the purchase office to the sales office or service office, is not yet invoiced. In this case, you cannot delete the purchase order line before the sales order or service order is invoiced.

Categories