Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
27891 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

FirstLast

Tips: LN | Baan

Categories