Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article BPCS/LX Tip of the Week: What is Lean Make to Order?
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
115906 Rate this article:
No rating

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Use this session to to define which fields must be audited, and when they must be audited.

Note: 

  • It is not required to define the fields that must be audited. Only if not all fields in a table must be audited, you must specify the fields that must be audited. You can only specify fields for a table for which you selected Specified in the Field Selection field of the Audit Tables by Profile (ttaud3120m000) session. If you selected All in that field, all fields in the table are audited, and no fields can be specified.

  • For a detailed explanation of the relation between audit type and field specification, refer to the section How to determine the net result of the audit configuration in the Audit Configuration Management topic.

  • The audit functionality uses the positive approach, which means that you can only specify which tables and fields must be audited, but not which tables and fields must not be audited. Therefore, through the appropriate menu, commands are available to load all (key) fields. You can then delete the fields you do not require.

Categories