Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

Previous Article BPCS/LX Tip of the Week: Actual Costs for Manufactured Items
Next Article Baan/LN Tip of the Week: Switching to a Difference Series
Print
32288 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

When to use a user defined inventory transaction

ERP LX (BPCS) provides you with the flexibility to create inventory transactions without program modifications. The typical transaction types are defined with effects set on how the transaction will impact inventory balances.

Perhaps you want to process a customer return and don’t want to the inventory to be impacted. You can create a user define transaction effect to allow the customer receipt and not update the inventory balance.

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.