Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
27905 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

 

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash f

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

FirstLast

Tips: LN | Baan

Categories