Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
Previous Article Partner News: How does Infor LN fit the industries that it serves?
Next Article Why should you look at OTTO? Let’s see what an OTTO customer has to say:
Print
56753 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.