Infor LN & Baan: What are your production orders telling you?

Measure what you want to improve.

Six simple words, but put together they convey a powerful concept that can transform manufacturing companies. It’s a basic concept that’s hard to argue with: Collect data, see where the data leads you, and make changes that have a positive impact on the data. Repeat often.

If your company is manufacturing a product, you’re more than likely creating manufacturing variances. These variances tell managers where the company is not performing to the standards that were created and agreed to by those responsible in the Engineering, Finance, or Production Departments. There is almost a 100% chance you are creating either favorable or unfavorable manufacturing variances and, quite frankly, none of the variances will ever be favorable because the company is either over-costing or under-costing the production parts.

The data is all there within your ERP system… or at least it should be… provided that you are not tracking production information outside of your ERP system in a spreadsheet.

Analyzing your production orders can help you track down:

  • Missing labor entries
  • Incorrect labor standards
  • Incorrect time estimates for routing steps
  • Inaccurate or non-existent material issues
  • Work order structures that are not accurate
  • And more


Crossroads also offers a Production Order Variance Report package for Baan and Infor LN which quickly identifies problems with pricing, materials, efficiency, and rejects. learn more> 

Not sure where to start? Crossroads RMC’s supply chain and manufacturing audit can help identify problem areas in Purchasing, Customer Service, Billing, Inventory, Costing, Bills of Materials and Routings, Material Requirements Planning and Shop Floor Control, and more.

Request a Supply Chain & Manufacturing Audit, or Contact me today to learn more - 800.762.2077

Previous Article Infor LN & Baan Tip: MPS planned vs. MRP planned
Next Article Infor LX & BPCS Finance Tip: Items without costs, CST101D
Print
29500 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.