Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
21611 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Want to increase your efficiency across your organization?

Is access to real time data important to you?

Take a look at how and where your information is stored. Do you have employees keeping separate spreadsheets or databases outside of your ERP?

Separate data silos means that information is not being shared between departments. This can hamper growth, and cut down on overall efficiency. Take a look at why these silos exist. Can something be done within your ERP system to avoid having to store the information elsewhere? Can an integration be cre

ated to allow the ERP to have exposure to other databases, or allow updates to occur between systems?

Need help figuring out where to start? Contact us. We’d be happy to help.

Optimize Your Manufacturing Today!

  • Print Sales Order History Information - all invoices processed through sales
  • Check Inventory Valuation - this should tie out to your inventory accounts
  • Print Integration Information - see all postings from WIP to finished goods
  • Print G/L Transaction Information - print specific transaction types for any GL account
  • Print Lot Control Information - will show where serial numbers were used

Optimize Your Manufacturing Today!

FirstLast

Tips: LN | Baan

Categories