Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Avalara - AvaTax Integration to Infor LX, BPCS, Infor LN, Baan, and M3
Next Article Infor LN & Baan: What are your production orders telling you?
Print
65374 Rate this article:
3.8
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Such lofty goals you had when you implemented your ERP system. It was going to be like pressing the “Easy Button”…  then it wasn’t.

What happened? In some cases, decisions were made to implement the system “just like we used to run our old system”. Great idea? Not so much. Your business changes, and your business software needs to change as well.

Have you looked at streamlining your processes?Are you using the ERP system, but everything seems cumbersome and takes more time than its worth? Ask yourself these questions:

  • Can you automate a step or two and eliminate some manual keying?
  • Can you add barcoding to avoid keying in some information altogether?
  • How about automating the printing of some reports?

Now is the time to sit down and really review the steps required to complete the task and think out of the box a bit. Soon you can develop your own streamlined process to get the job done quickly and efficiently.

Optimize Your Manufacturing Today!

I hate getting lost. I feel out of control and helpless. Thank God my dad taught me early on how to read a map. Maps give us direction, points of reference, and helps us navigate the obstacles in our way.  

Do you have roadmap for your ERP system, or are you lost? An ERP roadmap can give your staff direction. It should help you create a stronger workforce that is well prepared to meet the future needs of your business. Take a hard look at what your ERP is, or isn’t doing for you. Chances are, there is much that can be done, and all you need to do is start plotting out your map. 

Optimize Your Manufacturing Today!

FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.