Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
27973 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Such lofty goals you had when you implemented your ERP system. It was going to be like pressing the “Easy Button”…  then it wasn’t.

What happened? In some cases, decisions were made to implement the system “just like we used to run our old system”. Great idea? Not so much. Your business changes, and your business software needs to change as well.

Have you looked at streamlining your processes?Are you using the ERP system, but everything seems cumbersome and takes more time than its worth? Ask yourself these questions:

  • Can you automate a step or two and eliminate some manual keying?
  • Can you add barcoding to avoid keying in some information altogether?
  • How about automating the printing of some reports?

Now is the time to sit down and really review the steps required to complete the task and think out of the box a bit. Soon you can develop your own streamlined process to get the job done quickly and efficiently.

Optimize Your Manufacturing Today!

I hate getting lost. I feel out of control and helpless. Thank God my dad taught me early on how to read a map. Maps give us direction, points of reference, and helps us navigate the obstacles in our way.  

Do you have roadmap for your ERP system, or are you lost? An ERP roadmap can give your staff direction. It should help you create a stronger workforce that is well prepared to meet the future needs of your business. Take a hard look at what your ERP is, or isn’t doing for you. Chances are, there is much that can be done, and all you need to do is start plotting out your map. 

Optimize Your Manufacturing Today!

FirstLast

Tips: LN | Baan

Categories