Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
21722 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

With this enhancement, the Purchase Receipts screens are optionally shown with the quantity and weight fields populated with the open value on the purchase order.

Previously the user had tomanually enter the quantity received or, for a dynamic weight and measure items, the weightreceived for each line on the purchase order.

Now the screens are populated with the open valueand if the open value is the same as the value received, the user can simply accept the line.

Optimize Your Manufacturing Today!

So, how many of you have updated the estimated cost of material and labor in your ERP system recently? ……Hmmmm. That’s what I thought.

Do you have any idea how accurate those numbers are? Are you making business decisions based on estimates that are completely inaccurate?

Consider switching from estimates to actuals. Furthermore, consider implementing an automated data collection system to make this easy. By collecting production and labor data real time, you can gain real insight into your business and you gain the ability to look at the profitability of individual jobs, projects and employees.

Optimize Your Manufacturing Today!

FirstLast

Tips: LN | Baan

Categories