BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees
Print
54332 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

When a lot is completely shipped on a customer order, the Lot Status is changed to Z. Since a resupply order must still be received in the To Warehouse to complete the transaction, do not update the lot status when the resupply order is shipped. If a lot is completely shipped on a resupply order, LX no longer updates the lot status to Z, because the shipped lot retains its current lot status, the additional steps, no additional steps are required to receive it in the To Warehouse.

This feature resolves or resets a purchase order or requisition that is no longer being processed, but the system still indicates it is 'in use'. The user selects Purchase Order/Requisition in Use Maintenance, PUR940D, from the Purchasing Management Menu, PUR, located in the Special Processing sub-menu. The user then enters an order or requisition to remove the 'In Use' status.