Infor LX & BPCS Tip: Capacity Planning – Resource Requirements Reports

Resource Requirements Report (CAP260D) generates five capacity reports:

  • Labor Resource Requirements
  • Machine Resource Requirements
  • Setup Resource Requirements
  • Setup and Labor Requirements
  • Setup and Machine Requirements

The Labor Resource Requirement report lists requirements that are calculated from the run hours on each routing and the MRP/MPS demand in the Capacity Requirements Detail File (LCR). The calculation does not consider crew size.

The Machine Resource Requirement report lists machine hour requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The Setup Resource Requirements report lists setup labor requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The last two reports combine setup hours with labor hours and setup hours with machine hours to provide two separate reports that summarize the requirements by work center with totals by department. The system computes requirements similarly to the way it computes them on the other reports.

Have questions on this process or need some help? Contact us! Our experienced consultants will be glad to assist you.

800.762.2077

Previous Article 6 Ways Disconnected Data is Harming Your Business
Next Article Infor LN & Baan Tip: What is the GRNI Reconciliation Process?
Print
23235 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Note: The Blocked Operations (tisfc0540m000) session displays the blocked operations.

Introduction

Sometimes a problem occurs that must be solved before an operation proceeds. Examples of such situations are:

  • The quality of an intermediate product must first be inspected.
  • A machine is in repair.
  • A supplier cannot deliver an essential component in time.
  • A customer is late with its payments.

In these situations the operation can get the operation status Blocked.

An operation can be blocked:

  • Manually.
  • Automatically by Quality.

Blocking reasons

Every blocked operation must have a blocking reason. The blocking reason of a blocked operation has two purposes:

  • To indicate why the operation is blocked.
  • To determine which actions you can no longer perform on the operation.

Types of blocking

The following actions can be blocked by means of a blocking reason:

  • Reporting a quantity completed.
  • Reporting a quantity rejected.
  • Reporting a quantity to be inspected.
  • Reporting an operation completed.

You normally carry out these actions in the Report Operations Completed (tisfc0130m000) session.

You can define blocking reasons in the Blocking Reasons (tisfc2100m000) session.

Manual blocking

Use the Report Operations Completed (tisfc0130m000) session to block an operation. When you block an operation, you must also enter a blocking reason. If Quality has already blocked the operation, you can only enter a blocking reason, which is more restrictive than the blocking reason of Quality.

Blocking by Quality Managem