Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
35294 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Note: The Blocked Operations (tisfc0540m000) session displays the blocked operations.

Introduction

Sometimes a problem occurs that must be solved before an operation proceeds. Examples of such situations are:

  • The quality of an intermediate product must first be inspected.
  • A machine is in repair.
  • A supplier cannot deliver an essential component in time.
  • A customer is late with its payments.

In these situations the operation can get the operation status Blocked.

An operation can be blocked:

  • Manually.
  • Automatically by Quality.

Blocking reasons

Every blocked operation must have a blocking reason. The blocking reason of a blocked operation has two purposes:

  • To indicate why the operation is blocked.
  • To determine which actions you can no longer perform on the operation.

Types of blocking

The following actions can be blocked by means of a blocking reason:

  • Reporting a quantity completed.
  • Reporting a quantity rejected.
  • Reporting a quantity to be inspected.
  • Reporting an operation completed.

You normally carry out these actions in the Report Operations Completed (tisfc0130m000) session.

You can define blocking reasons in the Blocking Reasons (tisfc2100m000) session.

Manual blocking

Use the Report Operations Completed (tisfc0130m000) session to block an operation. When you block an operation, you must also enter a blocking reason. If Quality has already blocked the operation, you can only enter a blocking reason, which is more restrictive than the blocking reason of Quality.

Blocking by Quality Managem