Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 189 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is...

What are your production orders telling you?

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 134 Article rating: 5.0

MEASURE WHAT YOU WANT TO IMPROVE!

Six simple words, but put together they convey a powerful concept that can transform manufacturing companies. It’s a basic concept that’s hard to argue with: Collect data, see where the data leads you, and make changes that have a positive impact on the data. Repeat often.

If your company is manufacturing a product, you’re...

Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

George Moroses 0 75 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

LX User Group Event: Infor Partner Spotlight | Crossroads RMC

Tuesday, May 10 | 12:00pm - 1:00pm ET

Crossroads RMC 0 108 Article rating: 5.0

LX User Group Event

Tuesday, May 10 | 12:00pm - 1:00pm ET
Infor Partner Spotlight | Crossroads RMC

Come hear recent success stories with Crossroads RMC's software MES Ultimate, Analytics Dashboard, and Avalara's interface, along with consulting services that focus on a joint upgrade and MES project with Infor.

Register now →

Crossroads RMC Welcomes Robert Brown!

Crossroads RMC 0 236 Article rating: 5.0

Crossroads RMC Welcomes Robert Brown, as a Sr. Business Consultant!
Bob brings 30+ years of shop floor and project management skills to Crossroad RMC. He is a self-starter that has progressively mastered the Manufacturing, Supply Chain, and Finance modules within Infor LX. Bob will get started with EDI/ECM set up for new trading partners and within the Supply Chain ranks. Bob is a great addition to the Crossroads RMC team, and we look forward to his leadership expertise on implementations and upgrades in the near future.

RSS
1345678910Last

Theme picker