Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES:
Next Article Infor LN & Baan Tips & Tricks for Technology: Using audit files in the Exchange module
Print
35347 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Leave a comment

This form collects your name, email, IP address and content so that we can keep track of the comments placed on the website. For more info check our Privacy Policy and Terms Of Use where you will get more info on where, how and why we store your data.
Add comment

Contact author

x